Substation installation and comprehensive electrical works for M/s Jackson & Company at their Bhiwadi industrial facility. The project included installation of a 500 KVA, 11 KV transformer with HT panel and RTCC panel, 4 pole structures, HT cable works with CT/PT cubicle panel, LT panels, internal lighting, and earthing systems. Project cost: ₹3.00 Cr.

M/s Jackson & Company — Bhiwadi, Rajasthan
Project Details
| Client | M/s Jackson & Company |
| Location | Bhiwadi, Rajasthan |
| Completion | 2024 |
| Scope of Work | Installation & commissioning of 500 KVA, 11 KV transformer/HT panel/RTCC panel — 4 pole structures; HT cable/HT CT/PT cubical panel/HT termination on HT side; installation & commissioning of LT panels; supply & installation commissioning of internal lighting; supply & installation commissioning of earthing systems. |
Challenge
Erecting heavy 4-pole substation structures and terminating 11 kV high-tension lines adjacent to existing high-voltage feeder networks under strict regional utility safety clearance windows.
Solution
Utilized precision crane rigging with specialized hot-line safety supervision, pre-calibrated RTCC and protective relays off-site, and conducted high-potential (Hi-Pot) and transformation ratio testing to achieve flawless single-pass energization.